An audit report on the Clark International Airport Corporation shows the project has been extended six times, adding 930 days to the original 365-day contract, An audit report on the Clark International Airport Corporation shows the project has been extended six times, adding 930 days to the original 365-day contract,

Auditors flag P290-M Clark air traffic control tower project delays, cost overruns

2025/12/12 09:14

MANILA, Philippines – State auditors flagged the P290.3-million New Clark Air Traffic Control Tower project, awarded in January 2021 and expected to be completed within a year, saying it remains unfinished with no target turnover date.

The 2024 audit report on the Clark International Airport Corporation (CIAC) showed the project has been extended six times, adding 930 days to the original 365-day contract, but was only 91% complete as of 2024. Costs had also risen 22% to P354.41 million.

Auditors attributed the delays to weak procurement planning, poor project monitoring and possible shortcomings in the contractor’s capacity. They also noted the project broke ground without the required building, electronic, electrical, mechanical, plumbing and sanitary permits from the Clark Development Corporation, the regulator for the Clark Freeport Zone.

Auditors stressed that building permits are mandatory under the National Building Code, with violations carrying fines of up to P20,000 or jail terms of up to two years.

“It was only on April 29, 2024 that CIAC was able to secure the necessary permits from the CDC. The absence of necessary permits during the construction period raises serious concerns regarding regulatory compliance, project authorization, and risk management,” the report read in part.

Auditors said the missing permits reflected poorly on the contractor’s ability to plan and questioned why construction continued for years without them.

“Securing permits is a fundamental requirement in the construction industry, and failure to do so casts doubt on the contractor’s capability to manage regulatory requirements effectively. This oversight not only hindered the project’s progress but also highlighted deficiencies in due diligence and adherence to standard construction protocols,” the report added.

State auditors said CIAC management failed to intervene early, allowing procedural violations to persist.

The contractor sought a suspension of the height clearance limit on March 17, 2022 – two months after the original January 2022 completion date – after the Civil Aviation Authority of the Philippines (CAAP) denied permits for the tower and tower crane for exceeding allowable height. The control tower’s proposed top elevation was 228.81 meters, compared with CAAP’s 192-meter limit, a 36.81-meter excess.

The report noted that the approval of the Final Aeronautical Study and the redesign of the 4-Instrument Flight Procedures remained pending.

With shortening the tower out of the question, CAAP required an aeronautical study for a height clearance exemption. COA said the study assessed deviations from aerodrome standards, proposed safety measures, and recommended procedures to offset the deviation.

The contractor commissioned an international firm in 2023 to conduct the three-month study, costing P3.9 million. A portion of the findings stressed that “considering the existing defenses and proposed mitigation measures, the risks associated with the new control tower in its final situation are deemed acceptable.”

The results, along with a new Height Clearance Permit application, were submitted to CAAP on October 11, 2023. As of December 31, 2024, the permit had not been issued.

“Further verification revealed that CAAP requires additional documentation to support the aeronautical study report,” the audit showed.

Auditors also found the installed elevators did not match the specified brand in the paid progress billings. While the project listed a German-made Schneider elevator, inspection revealed a different brand.

They said, “According to the approved Bill of Quantities, the contracted brand was Schneider, a German brand. However, during an inspection conducted on March 20, 2025, the installed elevator was identified as Global Fuji, a Chinese brand. A review of records confirmed that this substitution was approved by the then president and chief executive officer of CIAC.” – Rappler.com

Disclaimer: The articles reposted on this site are sourced from public platforms and are provided for informational purposes only. They do not necessarily reflect the views of MEXC. All rights remain with the original authors. If you believe any content infringes on third-party rights, please contact [email protected] for removal. MEXC makes no guarantees regarding the accuracy, completeness, or timeliness of the content and is not responsible for any actions taken based on the information provided. The content does not constitute financial, legal, or other professional advice, nor should it be considered a recommendation or endorsement by MEXC.

You May Also Like

Polygon Tops RWA Rankings With $1.1B in Tokenized Assets

Polygon Tops RWA Rankings With $1.1B in Tokenized Assets

The post Polygon Tops RWA Rankings With $1.1B in Tokenized Assets appeared on BitcoinEthereumNews.com. Key Notes A new report from Dune and RWA.xyz highlights Polygon’s role in the growing RWA sector. Polygon PoS currently holds $1.13 billion in RWA Total Value Locked (TVL) across 269 assets. The network holds a 62% market share of tokenized global bonds, driven by European money market funds. The Polygon POL $0.25 24h volatility: 1.4% Market cap: $2.64 B Vol. 24h: $106.17 M network is securing a significant position in the rapidly growing tokenization space, now holding over $1.13 billion in total value locked (TVL) from Real World Assets (RWAs). This development comes as the network continues to evolve, recently deploying its major “Rio” upgrade on the Amoy testnet to enhance future scaling capabilities. This information comes from a new joint report on the state of the RWA market published on Sept. 17 by blockchain analytics firm Dune and data platform RWA.xyz. The focus on RWAs is intensifying across the industry, coinciding with events like the ongoing Real-World Asset Summit in New York. Sandeep Nailwal, CEO of the Polygon Foundation, highlighted the findings via a post on X, noting that the TVL is spread across 269 assets and 2,900 holders on the Polygon PoS chain. The Dune and https://t.co/W6WSFlHoQF report on RWA is out and it shows that RWA is happening on Polygon. Here are a few highlights: – Leading in Global Bonds: Polygon holds 62% share of tokenized global bonds (driven by Spiko’s euro MMF and Cashlink euro issues) – Spiko U.S.… — Sandeep | CEO, Polygon Foundation (※,※) (@sandeepnailwal) September 17, 2025 Key Trends From the 2025 RWA Report The joint publication, titled “RWA REPORT 2025,” offers a comprehensive look into the tokenized asset landscape, which it states has grown 224% since the start of 2024. The report identifies several key trends driving this expansion. According to…
Share
BitcoinEthereumNews2025/09/18 00:40
Fed Makes First Rate Cut of the Year, Lowers Rates by 25 Bps

Fed Makes First Rate Cut of the Year, Lowers Rates by 25 Bps

The post Fed Makes First Rate Cut of the Year, Lowers Rates by 25 Bps appeared on BitcoinEthereumNews.com. The Federal Reserve has made its first Fed rate cut this year following today’s FOMC meeting, lowering interest rates by 25 basis points (bps). This comes in line with expectations, while the crypto market awaits Fed Chair Jerome Powell’s speech for guidance on the committee’s stance moving forward. FOMC Makes First Fed Rate Cut This Year With 25 Bps Cut In a press release, the committee announced that it has decided to lower the target range for the federal funds rate by 25 bps from between 4.25% and 4.5% to 4% and 4.25%. This comes in line with expectations as market participants were pricing in a 25 bps cut, as against a 50 bps cut. This marks the first Fed rate cut this year, with the last cut before this coming last year in December. Notably, the Fed also made the first cut last year in September, although it was a 50 bps cut back then. All Fed officials voted in favor of a 25 bps cut except Stephen Miran, who dissented in favor of a 50 bps cut. This rate cut decision comes amid concerns that the labor market may be softening, with recent U.S. jobs data pointing to a weak labor market. The committee noted in the release that job gains have slowed, and that the unemployment rate has edged up but remains low. They added that inflation has moved up and remains somewhat elevated. Fed Chair Jerome Powell had also already signaled at the Jackson Hole Conference that they were likely to lower interest rates with the downside risk in the labor market rising. The committee reiterated this in the release that downside risks to employment have risen. Before the Fed rate cut decision, experts weighed in on whether the FOMC should make a 25 bps cut or…
Share
BitcoinEthereumNews2025/09/18 04:36